Present status of various housing schemes under CGEWHO

Present status of various housing schemes under CGEWHO

The below detailed information was reported as written reply to a question in Lok Sabha on 13.3.2013 by the Minister of Housing and Urban Poverty Alleviation Shri.Ajay Maken as follows...

As reported by CGEWHO, housing schemes under the organization to provide houses to Central Government Employees in different parts of the country are as under : -

Housing projects where  construction is in progress are:Housing projects under planning are:
i.Chennai (Ph-II);i. Vishakapatnam;
ii.Mohali (Ph-I); ii. Meerut (Ph-II);
iii.Bhubaneswar (Ph-I);iii. Greater Noida;
iv.Meerut (Ph-I); iv. Chennai (Ph-III);
v.Kolkata(Ph-II); v. Mohali (SAS Nagar)
vi.Bhubaneswar(Ph-II);
vii.Mohali (Ph-II)

As reported by CGEWHO schemes are planned after conducting a demand survey and thereafter making attempts to acquire land from State Government Authorities. In case of non-availability of land from State Government Authorities, housing schemes are planned as turnkey projects wherein land is also provided by the construction agency. Hence no definite time frame can be planned for such housing schemes.

Allotment of houses under each Scheme is made to eligible applicants after the draw. The specific allocation of dwelling unit number in a particular project is made at the time of the completion of the project. Allotment has been made in the following housing schemes:

Schemes Time Schedule
i. Chennai (Ph-II); Within three months
after formal closure
of the scheme,
allotment has been
made in all the
schemes.
ii. Mohali (Ph-I);
iii. Bhubaneswar (Ph-I);
iv.< Meerut (Ph-I);
v. Kolkata (Ph-II);
vi. Bhubaneswar (Ph-II); and
vii. Mohali (Ph-II);

CGEWHO housing schemes are initially planned with an anticipation of getting the processes completed as per estimates and plan. However, prior permission has to be obtained from statutory municipal and development authorities and No Objection Certificates from related state departments like fire, airport, environment etc. before commencement of construction.

Even after the completion of the works, the requisite completion/occupancy certificate from the statutory authorities and subsequent service connections viz. electricity, water, sewage etc. also get delayed which are beyond the control of CGEWHO.

Comments

Popular posts from this blog

Central Government Office Holiday List 2023 - DoPT Order PDF Download

7th CPC Pay Fixation on Promotion/MACP Calculator with Matrix Table

Revised Pay Scale from 1.7.2017 for Karnataka Govt Employees